God blessed us greatly when a member of parish family, Darrell Boldt, agreed to serve as general contractor for improvements to our worship space.  Darrell remodeled the current offices in Hafer House a number of years ago.  He probably knows our structures better than anyone!  His company, D. A. Boldt Construction, has been a respected member of the Southern Oregon building community since 1972.  Many, many thanks, Darrell!!

TIMETABLE

August 2             

8:00 & 10:00        Holy Eucharist services in the church

2:00                       Come help the Worship Commission move our worship into the parish hall!

August 3                                            

Piano will be moved and the organ protected.

August 4   

Pews will be moved out for refinishing.

Construction Begins!

August 9             

8:00                        Holy Eucharist service in the parish hall

10:00                     Ecumenical worship & picnic at Alba Park