Recent Church Developments:

  • Painting and electrical work are nearly finished.
  • The protective plywood floor and the scaffolding will soon be removed.
  • Heaters in the church and Hafer House have been cleaned, serviced and made ready for winter.
  • Our generous parishioner, Barry Johnson, installed a new sump pump in the church basement, another preparation for winter and increased rain.

Recent Hafer House Developments:

  • The Medford Water Commission inspected and signed off on the lot line adjustment.
  • Medford Public Works completed a sewer dye test and signed off on the lot line adjustment.
  • The appraisal of Hafer House is finished and will become official once the lot line adjustment is completed.
  February 2020  
SMTWTFS
      1
2345678
9101112131415
16171819202122
23242526272829
     
Today's Events
FEB

25

TUE
Shrove Tuesday Pancake Supper
5:30 PM to 7:00 PM
Mark's Men invite the parish and guests to our annual Shrove Tuesday Pancake Supper in the Hafer House Ballroom!