B & G Update: September 6, 2015

Buildings and Grounds Update

Developments this week:

  • In the church, the drywall and trim have been repaired.  
  • Drywall on the newly vaulted narthex ceiling has been installed.  
  • Painters are halfway through masking the beams and walls in preparation for spray painting the ceiling.